Dominion Logo Have You Seen D Today
Customer Service Products News Investors About Us Contact Us
» Search
GO
Powerline Projects
Home Page
About Us
Our Contacts
Regulatory Resources
Fact Sheet
Bristers-Gainesville 230 kV Line

Project Scope 

The proposed project is necessary to assure that the Company’s transmission facilities continue to meet projected load growth in a reliable manner consistent with North American Electric Reliability Council (NERC) Planning Standards for transmission facilities. Load growth in the northern Piedmont area will push the capability of the existing 500-230 kV transformers located in this region past their capacity should there be a loss of some of the critical lines or transformers, resulting in customer outages. Also, Dominion Virginia Power and Northern Virginia Electric Cooperative (NOVEC) have identified a need for additional facilities in this area to provide service to their customers. The proposed new transmission facility will provide the means for solving these reliability issues and also provide for the orderly expansion of the transmission system in this area.

In order to bring in additional power to meet the increased load, create an alternate transmission source, and meet utility standards for contingency planning, Dominion proposes to build a 230 kV line between its future Bristers Switching/Substation in Fauquier County and its Gainesville Substation in Prince William County. The proposed line would be entirely within an existing right-of-way and parallel to the existing Morrisville-Loudoun 500 kV Line. This right-of-way was purchased in the late 1960s. We propose to locate the new 230 kV structures adjacent to the existing 500 kV structures so the wire spans will match. We are proposing a lattice type structure that will be approximately the same height as the existing structures, and ultimately support two 230 kV circuits. In association with this project, Dominion will replace the electric conductor wires on a transmission line from Gainesville Substation north to our Loudoun Substation. As a separate project, we also propose to construct a new substation in the Nokesville area by 2010.

Project Details 

Approximate line length:

16 miles

Right of way width:

240 feet 

The northern 8.6 miles of the right-of-way is cleared to its full width of 240 feet. The centerline of the 500 kV line is 75 feet from the western edge of the right-of-way and there is an electric distribution line that occupies the eastern edge of the right-of-way.

The remaining 7.1 miles on the southern end of the project is cleared to a width of 150 feet on the western side for the existing 500 kV line. The new line will require that the additional 90 feet be cleared on the eastern side of the right-of-way.

Typical pole description:

Lattice 230 kV double circuit structures are proposed. See the proposed structure.

Structure height:

130 feet tall.  

Strucuture spacing:

Approximate 1100-foot span, to match the existing 500 kV line’s structure locations as closely as possible.

In-service date:

May 2009  

Total estimated cost: $20 million

Project Update

The Virginia State Corporation Commission issued its final order on November 13, 2006, approving the proposed Bristers-Gainesville 230 kV Line.

Tentative Schedule of Project

Spring 2006

  • Meet with Fauquier County and Prince William County officials to discuss projects. 
  • Public Information Meetings 
  • File Application for approval of project with the State Corporation Commission

Winter 2006

  • SCC Public Hearings to receive public statements and evidence.
     

Spring 2007

  • SCC Hearing Examiners Report 
  • SCC Ruling
  • Wetland Delineation
  • Archaeological Survey
  • Construction Permits
     

Summer 2007

  • Begin Construction
     

December 2008

  • Complete new line construction
     

May 2009

  • Complete conductor replacement of the existing Gainesville-Loudoun line
     

 

Fact Sheet
Map
Questions & Answers