The State Corporation Commission (SCC) approves all electric
transmission facilities of 150,000 volts (150 kV) or more in Virginia, which
includes this project. After the Company files its application, the SCC will
issue an order setting the procedural schedule. The SCC will require Dominion
to publish the order in local area newspapers and write notification letters,
including the dates and locations of any public hearings and the dates the company
and interested parties (Respondents) must file testimony. A SCC Hearing Examiner
typically serves as a judge at the hearings. Afterwards, the Hearing Examiner
will issue a report to the three SCC Commissioners. The Commissioners will review
all of the evidence and the Hearing Examiner’s recommendation before deciding.
Select "SEARCH CASES" on the navigation across
the top of the page. Enter the Case Number in the "Enter Case Number"
field and click on "Search."
| Volume I |
|
| Volume II |
|
| Volume III |
|
| Supplemental Direct Testimony - 07-13-2007 |
- SCC Cover Letter
- Stephen G. Thornhill - Revised aerial maps were included with this supplemental testimony.
- Elizabeth Harper
- Testimony
- Summary of Changes
- Maps - (revised 10/02/07) This file includes an index sheet and 11 maps. (This file includes an index sheet and 11 maps. Individual maps can be viewed by clicking on the boxes on the index sheet or by using the bookmarks.)
|
| Order of Notice and Hearing |
|
| Second Supplemental Direct Testimony - 10-03-2007 |
- Stephen G. Thornhill - Revised aerial maps were included with this supplemental testimony.
- Elizabeth Harper
- Testimony
- Summary of Changes
- Maps - (revised 10/02/07) This file includes an index sheet and 11 maps. (This file includes an index sheet and 11 maps. Individual maps can be viewed by clicking on the boxes on the index sheet or by using the bookmarks.)
|
| Hearing Examiner's Report |
|
|