Dominion Logo Have You Seen D Today
Customer Service Products News Investors About Us Contact Us
» Search
GO
Powerline Projects
Home Page
About Us
Our Contacts
Regulatory Resources
Fact Sheet
Kitty Hawk-Colington-Nags Head
Second 115kV Line

Project Purpose 

The existing 115kV Line No. 52 from Kitty Hawk to Nags Head is rated for 193 MVA. The 2004 summer peak was 144 MVA. The maximum load capacity is forecasted to be reached by 2012. This single radial transmission line serves approximately 25,000 customers. Excluding CHEMC load, improvements on our distribution circuits have increased the tie capability to carry the load 95% of the year and 79% of the time during summer peak. The 7.4-mile 2nd 115kV line will alleviate overloading of the existing line, provide an additional transmission source for the load area and improve reliability by eliminating outages for the single contingency loss of the existing transmission source south of Kitty Hawk.

Location

The line will extend east from Kitty Hawk Substation on NCDOT right of way on the south side of Route 1206. The single pole structures continue along the eastside of Route 158 on NCDOT right of way to the existing transmission structures south of Bonnett Street. An encroachment request for this project was approved in March, 2005. View simulations of the planned line and the structures along Rt. 1206 and Rt. 158.

Planned System Improvements for the Outer Banks Service Area

  • Express distribution circuit Kitty Hawk-Colington-Nags Head completed in 2004
  • Adding 3rd 230kV transmission line to Shawboro by May, 2005
  • Adding 75 MVA 230-34.5kV transformer at Kitty Hawk in June, 2005
  • Adding 33MVA 230-34.5kV transformer at Point Harbor in October, 2005
  • Adding new microwave communications for Kitty Hawk, Colington and Nags Head by December, 2005
  • Adding this 115kV transmission line from Kitty Hawk to Colington in May, 2007
  • Extending 2nd 115kV transmission line from Colington to Nags Head in May, 2009

Benefits 

  • Provides the necessary service to support the continued economic growth in the Outer Banks
  • Provides an additional transmission source for the area
  • Eliminates overloading of the existing transmission source after 2012
  • Eliminates outages for the contingency loss of the existing transmission source
  • Expedites the restoration of service to customers by minimizing outage frequency and duration
  • Improves voltage stability during peak load periods
  • Provides improved power quality
     


 
Overview
Fact Sheet
Map
Questions & Answers