SCC Approval
Pleasant View-Hamilton Project
Case No. PUE-2005-00018
Printer Version Print-Friendly Version

Five alternative routes were evaluated ranging from approximately 12.0 miles to 15.3 miles in length.  Both full length and partial length underground options were considered.  A Final Order approving the 230kV overhead line was received on February 15, 2008.

SCC Findings Highlights

House Bill 1319

On March 6, 2008 the General Assembly established a pilot program (House Bill 1319) to underground certain high voltage transmission lines within the Commonwealth. This bill has passed both houses of the General Assembly and was approved by Governor Timothy M. Kaine on April 2, 2008.  The first project to be part of this pilot program is a portion of the Pleasant View to Hamilton 230 kV line.

The portion of the Pleasant View-Hamilton line being considered for underground installation would be about 2 miles long. It would be located just west of Leesburg in the vicinity of Dry Mill Road and placed within W&OD Trail property. This section of the route is identified as Segment Trail B (see Approved Route Map).

On May 21, 2008, Dominion filed a "Modified Request" with the Virginia State Corporation Commission for the underground portion of this project that relates to the pilot, under 2.A of HB 1319 (>> View this filing: Modified Request). On May 28, 2008, Dominion received approval for this request (>> View this order: Case No. PUE-2008-00042).