| Project Schedule Pleasant View-Hamilton 230kV Line |
| 2008 | |
| April | Send letters requesting release to survey |
| April-September | Survey property (survey crew, soil borings, archeology, environmental survey) |
| April-November | Purchase easements |
| December | Tree clearing starts |
| December | Foundation installation starts |
| 2009 | |
| March | Structure installation starts |
| 2010 | |
| May | Transmission line in service |