Virginia City Hybrid Energy Center

Virginia City Hybrid Energy CenterVCHEC construction as of mid-June, 2010.

Artist's Rendering of the VCHECArtist's Rendering of the VCHECThe 585-megawatt Virginia City Hybrid Energy Center is part of Dominion’s response to meeting a projected growth in demand for electricity of 4,000 megawatts from its customers by 2017, or enough electricity to power one million homes. 

Virginia City will be one of the cleanest power stations of its kind.  The circulating fluidized bed unit will use coal and up to 20 percent biomass for its fuel.

A Virginia Tech economic impact study concluded that the station will generate about $440 million a year in tax revenues and other benefits for Wise County.

Contact us if you need additional information or have questions.

Latest News and Construction Updates

  • Construction Updates and Photos  — Select Construction Updates below for details.
  • Virginia City Hybrid Energy Center Project Reaches Safety Milestone View the news release (06/21/10).
  • Quarterly Newsletter — (Vol. 7, April 2010) for residents of Virginia City, Wise County and the region.
  • Dominion Virginia Power Gets Amended Air Permit — View the news release (10/02/09)
  • Carbon-Capture and Storage Demonstration Proposed — View the news release (08/25/09) and an artist's rendering.
  • Employment Opportunities  — Contact the Shaw Employment Warehouse Facility at 276-762-5585.

Project Details

Construction Updates

Update for July 2010 — 400-Ton Generator Component Arrives at Dominion Power Station Project in Wise County

A convoy bringing a 400-ton component to Dominion's Virginia City Hybrid Energy Center project arrived on the construction site on July 7.

The arrival of the stator – the largest stationary component of the new electric generator – marks a major milestone in the construction of the 585-megawatt power station. Construction began in June 2008 and is approximately 65 percent complete. The station is on schedule to begin generating electricity commercially in the summer of 2012.

The $1.8 billion power station will produce enough electricity to power 146,000 typical homes at peak demand. The project is part of the company's "Powering Virginia" plan to help meet the growing electricity demand of Dominion Virginia Power customers.

"The stator's arrival puts one more big piece in place," said Charlie Scott, project manager at Virginia City. "This effort required a tremendous amount of teamwork, planning and coordination from numerous resources as well as local and state agencies in Virginia and Tennessee. Dominion greatly appreciates the efforts of all who made this accomplishment possible."

A jacking system was used to lift the stator into place on the fourth story of the station's turbine generator building. The generator's major moving part, the rotor, arrived earlier at the station.

The stator completed a 176-mile, two-week journey from a river port in Knox County, Tenn. The generator component was manufactured by Toshiba in Japan, shipped to Port Allen, La., and barged to a dock on the French Broad River east of downtown Knoxville, where it arrived in February.

The stator and the hauling rig that brought it to the power station construction site weighed a combined 640 tons. During the Virginia portion of its journey, the rig stretched for 265 feet and was 22 feet wide and more than 17 feet tall. The rig was powered by two trucks manufactured by the Pacific Truck and Trailer Co. – "Big Daddy" at 700 horsepower and "Big John" at 600 horsepower. Numerous state police vehicles, utility bucket trucks and escort vehicles of Barnhart, the heavy-haul company in charge of the move, accompanied the rig on its journey.

The rig provided a late-night or early-morning show for towns along the route. Residents brought out lawn chairs to await the rig's late-night arrival through their town and took pictures of the slow-moving caravan.

Barnhart manager Tim Fielder says the Knoxville-to-St. Paul haul was the longest of this weight in the company's 41-year history.  The hauling rig and its payload were also one of the largest loads to travel Virginia highways, according to the Virginia Department of Transportation.

Tranportation images:

Installation images:


Update for March 2010 — Dominion power station continues on schedule

Work has moved forward on Dominion's Virginia City Hybrid Energy Center project over the past several weeks despite the "old-fashioned" winter that visited Southwest Virginia.

"The project is generally going to plan," said Mark Mitchell, Director-Fossil & Hydro Projects, for Dominion. "Most of the major [material and equipment] deliveries have been accomplished."

The overall project, which includes planning, engineering and construction, is now roughly 58 percent complete and remains on schedule for the start of commercial operations in the summer of 2012.

At the beginning of March, 1,335 people were employed on the project. Of that total workforce, 489 workers (or 36.6 percent) came from the local region, with Wise and Russell counties leading the way.

"We continue to employ good workers from Southwest Virginia," Mitchell said. The percentage of the project's workforce that comes from Southwest Virginia is higher than had been expected, he said. "They are good, hard workers."

The project has reached the milestone of 4 million man-hours worked without a lost-time accident. This milestone was reached as the transition from heavy steel erection to the installation of major internal components began at the project.

Recent major work has included boiler installation and the final preparation for the installation of the $1.8 billion power station's steam turbine and generator. Three-fourths of the major water-wall panels for one of the station's two 330-megawatt equivalent boilers had been raised into place by March 1.

Some of the bigger construction cranes, which have been an object of local curiosity, will be leaving the site later this year and the remaining structural steel will be hoisted into place. The station's permanent administration building, which will contain the control room, should be ready for occupancy later this year, too.

The high-voltage transmission line that will carry power from Virginia City to the regional grid via Appalachian Power's Clinch River station at Carbo is under construction and will be completed in October. In November, the energizing and testing of equipment will begin at Virginia City.

Construction hiring will continue on the project over the next few weeks until the total construction workforce nears 1,600 around mid-year. The hiring of the permanent operations staff also has begun. Preston Sloane, who most recently was station director at Dominion's Chesapeake Energy Center, has been named station director for Virginia City and is now living and working in the area.


Update for Dec. 16, 2009 — Virginia City Hybrid Energy Center Passes the Halfway Point

Dominion Virginia Power's Virginia City Hybrid Energy Center project in Wise County has passed the halfway point and remains on schedule.

Dominion, which operates Virginia's largest electric utility, is building a 585-megawatt power station at Virginia City to help meet the state's growing power needs. The station will be fueled by run-of-mine coal, waste coal and biomass in the form of wood chips.

More than 1,300 men and women are working on the project as of Dec. 1. Construction employment is expected to peak at around 1,500 next year.

Dramatic evidence of the construction progress is that only one level of steel remains to be erected to complete the framework for the 20-story-tall building that will house the station's two circulating fluidized-bed boilers. Also recently, the station's administration building has been topped out; three 13-story silos to house coal-combustion products have been poured; and workers have begun installing equipment in the station's coal, limestone and wood handling area. The station uses limestone to control sulfur dioxide emissions.

"Overall, we're about where we expected to be at this stage of the project," said Charlie Scott, Dominion site manager for construction at Virginia City. "We've certainly had our ups and downs, but not anything unexpected for a project of this size," he said.

Work on the $1.8 billion station began in the summer of 2008, and commercial operation is set to begin in mid-2012.

Preston Sloane, who was the station director at Dominion's Chesapeake Energy Center in Hampton Roads, has been named the Virginia City Hybrid Energy Center's first station director. Sloane has occupied an office at Virginia City and has begun filling out his permanent operations staff.

Other major work on the power station that will occur over the next few months includes: installation of a large bridge crane in the turbine-generator building, continued excavation of the station's dry-ash landfill and preparation of the turbine-generator building for installation of the generator's largest stationary part, which weighs 354 tons.


Update for Jan. 8, 2010


Update for Oct. 30, 2009

Images show the progress as of October 2009. Ash silos have been erected behind the chimney and the fourth (and final) tier of boiler-building steel is being constructed.


Update for Aug. 25, 2009

Aerial images show the progress as of August 2009.


Update for June 25, 2009

Work on Dominion's Virginia City Hybrid Energy Center was roughly 30 percent complete by mid-June. Foundations had been completed for most of the coal-fired power station's major buildings and the erection of structural steel for the boiler and steam turbine/generator buildings was well underway. Employment on the site was nearing 800 with roughly 25 percent of those workers having been hired from the local area. Construction employment is expected to peak at around 1,500 workers in 2010.


Update for April 20, 2009

Work continues to progress steadily at Dominion’s Virginia City Hybrid Energy Center since construction began in July 2008. The images below show construction of turbine pedestals and the first steel beams being installed.


Update for Feb. 11, 2009

Aerial images show the progress as of February 2009.


Update for Dec. 22, 2008

Construction of the concrete shell for the chimney at Dominion’s Virginia City Hybrid Energy Center topped out Tuesday, Dec. 16, at 486 feet. Following a long-standing tradition in the construction trades, the topping out was marked by the placing of a Christmas tree and an American flag at the top of the stack. The pouring of the concrete shell began Nov. 11 and finished a week ahead of schedule.

Jens Lehnnhoff, site manager for Karrena International, the subcontractor that built the chimney shell, described the project as a "normal job." A chimney project typically takes a little longer in winter than in warmer months because the concrete must be heated to cure properly, he said.

Still ahead for Karrena is the pouring of the concrete top or roof for the stack six feet below the top of its walls and installation of steel flues and a permanent elevator inside the concrete shell. Steel flues will eventually extend 20 feet above the roof. The entire chimney project is scheduled for completion next October.


Update for Dec. 8, 2008


Update for Nov. 18, 2008

A major milestone was reached Nov. 11 when workers began pouring the reinforced concrete shell for the power station’s 500-foot chimney. In addition to the boiler flues, the shell will contain an elevator capable of carrying workers to the 460-foot level. The shell will be equipped with temporary aviation warning lights during its construction and permanent lighting once it is complete.

The structure will sit on a foundation that includes 16 concrete pilings, each sunk 106-feet into the earth. The shell’s construction will require roughly 12 million pounds of concrete and 1.2 million pounds of steel reinforcement bar.

Elsewhere on the construction site, work is underway on a road from the future power station to a lined and engineered landfill where ash from the station will be hauled in large, off-road trucks and buried. Also, work is approaching the halfway point on the pouring of 465 underground concrete piers that will help support the foundation for the station’s various buildings.

One of three major bridges that will be built on the station property is complete and work has begun on another. Work is also progressing on the below-ground concrete vault that will house the electrical equipment for the power station. Additionally, wrap-up is near on construction of acceleration and turn lanes on U.S. Route 58A at the entrance to the site’s material-handling area, where coal, waste wood and limestone for the station’s boilers will be stored. A large metal pole to support a traffic signal at the intersection has been erected.

Project Resources
CFB Technology

Advanced circulating fluidized bed technology is proven clean-coal technology that also enables the using of run-of-mine coal, waste coal and renewable energy sources, such as wood waste. CFB technology combined with modern post-combustion controls has low emissions of sulfur dioxide, nitrogen oxide, particulate matter and mercury.

This technology is compatible with the need to be able to use a wide variety of fuels available in the region and compatible with the requirement to construct and operate a facility in an environmentally responsible manner that minimizes overall impact to air, water and land resources.

Site Selection

A Virginia City site near St. Paul, Va. (a reclaimed surface coal mine) was selected for the project. The Virginia City site meets the major criteria for the project to proceed, including an adequate fuel and water supply, electrical transmission requirements, construction logistics and minimal environmental impact.

Engineering, Procurement and Construction Contract

On February 23, 2007, The Shaw Group Inc. was awarded an engineering, procurement and construction contract by Dominion.

The preliminary scope of the agreement included a development phase to perform engineering, finalize major equipment selections and complete final cost estimates. Following completion of the development phase, Shaw continued with engineering, procurement and construction activities.

Local Benefits

Employment — The station will provide nearly 1,000 jobs during construction and require a permanent staff of more than 75 people once it begins operating.  It will create about 350 mining jobs. For information about employment opportunities at the construction job site, contact the Shaw Employment Warehouse Facility at 276-762-5585.

Tax Revenues and Benefits — A Virginia Tech economic impact study concluded that the station will generate about $440 million a year in tax revenues and other benefits for Wise County. The station, upon completion, will provide clean, reliable and economic electricity for Virginia families and businesses.

Fan Care — Dominion Virginia Power has expanded Fan Care to aid elderly in Southwest Virginia.

Station Rendering

An artist's rendering of how the station might appear upon completion is available for viewing or download. Choose from low-resolution or high-resolution versions.

Groundbreaking Ceremony

More than 300 state local officials and supporters joined Dominion executives on August 14, 2008, for the official groundbreaking ceremony for the Virginia City Hybrid Energy Center in Wise County.

Speaking from beneath a tent erected on the site of what eventually will be the 585-megawatt station's power block, Tom Farrell, chairman, president and chief executive officer, told the audience:

"The Commonwealth of Virginia needs this station. Without the Virginia City facility and others like it, our state would become increasingly dependent on high-priced electricity produced elsewhere — and risk losing the economic strength that led Forbes.com to name Virginia the best state in the nation in which to do business for the third year in a row."

"Wherever Dominion does business, we make a concerted effort to be a good corporate citizen and neighbor. Giving back to the community is an integral part of our heritage and corporate culture. In keeping with these values, Dominion would like to donate $25,000 to Mountain Empire Older Citizens, Inc... Our gift will go to Mountain Empire's emergency fuel fund, which helps the region's elderly residents pay their heating and cooling bills."

Joining Farrell on the speakers' platform were Virginia Lt. Governor William T. Bolling, Attorney General Robert F. McDonnell, Secretary of Commerce and Trade Patrick O. Gottschalk, State Senator William C. Wampler, State Senator Phillip P. Puckett and Delegate Clarence "Bud" Phillips.

Also Joining Farrell were Delegate Dan Bowling, Chairman Robert R. Adkins, Wise County Board of Supervisors, Mark F. McGettrick, President and CEO, Dominion Generation, James K. Martin, Senior Vice President, Dominion Business Development and Generation Construction, Duane Akridge, President of Wise County Chamber of Commerce, Joyce Payne, Executive Director of the Wise County Chamber of Commerce and Jonathan Belcher, Executive Director of the Virginia Coalfield Economic Development Authority.

Photos from the Event

Advertising

View our print ads (below) to learn more about our station. (Select either ad to view a larger version.) Also listen to our radio ad. These ads ran prior to receiving unanimous approval from the State Corporation Commission and the Virginia Air Pollution Control Board.

NYSE : (September 2, 2010) D 43.41 -0.45

Subscribe