The following items must be ready before Dominion can schedule work -

  • The underground cable route has been cleared of trees, stumps and other obstructions * (View examples)
     
  • The cable route is at final grade * (View examples)
     
  • Lot lines and corners have been staked
     
  • Stakes found missing must be replaced by your surveyors
     
  • All private underground facilities have been located and marked
     
  • The conditions listed must be maintained until electric service is installed
     
  • Meter base and customer conductors are installed (See “Information and Requirements for Electric Service”)
     
  • Obtain Electrical Inspection
     
  • Conduit installations must be marked and a pull string available (if required) *
     

* These requirements only apply to underground construction projects